Allows Metro to accept new water and sewer lines at 701 Donelson Pike (BNA NE Parking Lot): about 556 feet of eight-inch and 1,654 feet of 10-inch water main, about 1,974 and 682 feet of eight-inch sewer main, two fire hydrant assemblies, 15 sewer manholes and easements.
BL2026-1463
On the full council's agenda 3 times from January 2026, oldest first. Bills need three readings to pass; resolutions need one.
History
- July 7, 2026 · Bills on Introduction and First Reading Moving forward
Passed first reading; two more votes to go - July 21, 2026 · Bills on Second Reading Moving forward
Passed second reading; one more vote to go - August 4, 2026 · Bills on Third Reading Passed
Passed on third (final) reading