Lets Metro abandon about 253 feet of old eight-inch sewer main, three manholes and easements, and accept about 207 feet of new eight-inch sewer main, four new manholes and easements at 507 East Trinity Lane and East Trinity Lane (unnumbered). It costs Metro nothing.
BL2026-1545
On the full council's agenda 3 times from January 2026, oldest first. Bills need three readings to pass; resolutions need one.
History
- September 1, 2026 · Bills on Introduction and First Reading Moving forward
Passed first reading; two more votes to go - September 15, 2026 · Bills on Second Reading Moving forward
Passed second reading; one more vote to go - October 6, 2026 · Bills on Third Reading Passed
Passed on third (final) reading